| Sl. No. |
Scheme Name |
District |
Sanction Cost (Rs. In Lakh) |
| 01 |
Construction of Residential Building of Garhwal University |
Tehri |
809.510 |
| 02 |
District Jail |
Firozabad |
1055.610 |
| 03 |
NBFGR |
Lucknow |
1142.250 |
| 04 |
RMH, Azamgarh |
Azamgarh |
602.000 |
| 05 |
Varanasi Feeder Main Work |
Varanasi |
836.270 |
| 06 |
Alambagh Bus Stand |
Lucknow |
818.500 |
| 07 |
Trade Tax Office, Headquarters Building |
Lucknow |
595.790 |
| 08 |
Nurses Hostel |
Lucknow |
513.000 |
| 09 |
Construction of Godown of 67500 MT capacity at Rajya Bhandaran Nigam |
Moradabad |
1444.860 |
| 10 |
Construction of 1512 EWS Buildings and their related works |
Noida |
2551.405 |
| 11 |
Development work in Noida |
Noida |
2994.730 |
| 12 |
Collectorate (Non-Residential) |
Maharajganj |
573.410 |
| 13 |
Dr Bhimrao Ambedkar State Level Sports Complex |
Lucknow |
615.330 |
| 14 |
Construction of 800 MIG Bhawan |
Noida |
3864.900 |
| 15 |
Construction of Collectrate Building |
Udham Singh Nagar |
560.000 |
| 16 |
Resurfacing of Road, Sector-62 |
Noida |
887.750 |
| 17 |
Residential Building Type 2 & 3 |
Tehri |
742.910 |
| 18 |
Ganga Water Distribution Scheme (6497.47) |
Noida |
9467.470 |
| 19 |
Resurfacing Work of Various Sector's Road |
Noida |
1297.000 |
| 20 |
Construction of 58 nos Residential Building of Type 1,3 and 4 |
Tehri |
521.120 |
| 21 |
Scientific Convention Centre Phase-Ist. |
Lucknow |
2276.090 |
| 22 |
Construction of Collectrate Building |
Kaushambi |
550.200 |
| 23 |
Work in Pashulok |
Dehradun |
1100.000 |
| 24 |
Construction of Bridge and Road on Sarkata Nala |
Lucknow |
422.260 |
| 25 |
Construction work of Collectrate Building (Non-Residential) |
Bagpat |
534.160 |
| 26 |
Express Highway Electrification |
Noida |
1820.600 |
| |
COMPLETED WORK(TOTAL) |
38597.125 |
| 01 |
Sports Stadium |
Dehradun |
575.500 |
| 02 |
Almora Drainage Scheme (Phase I) |
Almora |
615.050 |
| 03 |
Development work sector 105 & 108 |
Noida |
4923.780 |
| 04 |
Construction of Sump Well of LDA |
Lucknow |
984.520 |
| 05 |
Construction of Tele Medicine, SGPGI |
Lucknow |
956.220 |
| 06 |
Construction of Heritage Center in Kapilvastu |
Siddharthnagar |
648.210 |
| 07 |
Construction of Institute of Pharmacy under University Campus |
Jaunpur |
780.000 |
| 08 |
Construction of Building of Mahamaya Agriculture Mechanical and Technological College |
Ambedkarnagar |
1025.250 |
| 09 |
Sewer Line Kalindi Ulhar |
Agra |
674.890 |
| 10 |
100 Beded Hospital |
Hathras |
719.260 |
| 11 |
Laying of Sewer Line at Greater Noida Express Highway |
Noida |
9833.400 |
| 12 |
Construction of Renney Wall |
Noida |
780.730 |
| 13 |
Construction of 544 Nos. HIG Building in Sector-105 |
Noida |
6988.030 |
| 14 |
100 Bedded Combined Hospital |
Chandauli |
642.470 |
| 15 |
Construction of Culvert, Drains and Road of Sector-46 & 93 |
Noida |
1107.840 |
| 16 |
District Headquarters Building (Non-Residential) |
Bhadohi |
694.900 |
| 17 |
Collectrate Building |
Auraiya |
541.720 |
| 18 |
Shastripuram Sewerage Scheme (Phase I + Phase II) |
Agra |
1458.550 |
| 19 |
Construction of 125 Bedded Combined District Hospital |
Udham Singh Nagar |
1315.850 |
| 20 |
Construction of Judisury Complex |
Udham Singh Nagar |
691.350 |
| 21 |
Sewarage Project, Jammu and DPR Sewarage Project |
Jammu |
1745.940 |